3700 Templeton Pl
Templeton
69% Complete
Project Progress
69% Progress

100% Timing

Start Date
March 1, 2022
End Date
August 3, 2022
1/1
Approved Documents
3/13
Complete Phases
50/82
Complete Tasks
Project Description

Bathrooms Renovation

Kitchen Renovation

Basement Demo- framing-renovation

Windows replacement

Floors replacement

Laundry renovation

Exterior repairs

Recess lights installation in most areas

ETC.

 

Edit Description
Documents
Phases
Expand Discussions | 3 / 13 Completed
Demolition 0 Documents 4 / 4 Tasks 0 Responses
100%
Description

Demo all the areas that will be renovated

No documents attached to this phase.
Leave a Reply
Kitchen Renovation 0 Documents 4 / 6 Tasks 0 Responses
85%
No documents attached to this phase.
Leave a Reply
Basement Framing/Renovation 0 Documents 6 / 6 Tasks 0 Responses
100%
Description

Frame half portion of the basement

Drywall installation in walls & ceilings in all the areas that were demo

No documents attached to this phase.
Leave a Reply
Hallway bathroom renovation (upper level) 0 Documents 8 / 9 Tasks 0 Responses
97%
No documents attached to this phase.
Leave a Reply
Master bathroom renovation & modification of layout 0 Documents 10 / 11 Tasks 0 Responses
100%
Description

Renovate / modify layout including removing a window and making adjustments inside and outside wall (exterior) to close the opening

No documents attached to this phase.
Leave a Reply
Half bathroom renovation 0 Documents 3 / 4 Tasks 0 Responses
98%
No documents attached to this phase.
Leave a Reply
Basement Bathroom renovation 0 Documents 1 / 7 Tasks 0 Responses
37%
Description

Frame & renovate entire bathroom

No documents attached to this phase.
Leave a Reply
General items (interior) 0 Documents 6 / 14 Tasks 0 Responses
80%
No documents attached to this phase.
Leave a Reply
General items (Exterior) 0 Documents 4 / 7 Tasks 0 Responses
75%
No documents attached to this phase.
Leave a Reply
Painting 0 Documents 0 / 7 Tasks 0 Responses
23%
No documents attached to this phase.
Leave a Reply
Haul/dispose 0 Documents 4 / 5 Tasks 0 Responses
90%
No documents attached to this phase.
Leave a Reply
Garage 0 Documents 0 / 2 Tasks 0 Responses
0%
No documents attached to this phase.
Leave a Reply
0 Documents 0 / 0 Tasks 0 Responses
0%
No documents attached to this phase.
Leave a Reply

Send Notification

Message Sent

Edit Phase
Add Phase
Project Discussion No discussions posted at this time
Loading
Add Document
Update Status
Document Status Updated
Notifications have been sent.